Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A new project manager is walking you through the schedule she has created for her project. She asks you about the duration of a particular milestone, so she knows how to properly schedule it. What will you tell her about a milestone’s duration?
A
It is shorter than the duration of the longest activity.
B
It is shorter than the duration of the longest activity.
C
It has no duration.
D
. It 1s the same length as the activity it represents.
Explanation: 

Detailed explanation-1: -A project manager should use the Develop Schedule process described by Project Management Institute (PMI) to create a project schedule. It is a process that helps determine the tasks to complete, the resources needed for those tasks, and the overall project timeline.

Detailed explanation-2: -What options are available to a project manager faced with a time constrained schedule that should have been resource constrained? Add more resources. Reduce project scope. What are the preferred approaches to assigning resources to activities?

Detailed explanation-3: -Define your project goals. Identify all stakeholders. Determine your final deadline. List each step or task. Assign a team member responsible for each task. Work backward to set due dates for each task. Organize your project schedule in one tool, and share it with your team. 18-Oct-2022