All of the following are true about resource leveling EXCEPT:
|
It can be used to keep resource usage at a constant level during certain time periods.
|
|
It can often cause the original critical path to change.
|
|
It is used to develop a resource-based WBS.
|
|
It is a resource optimization technique that can be used to adjust the schedule model due to demand and supply of resources.
|
Explanation:
Detailed explanation-1: -Resource Smoothening: In this method the total project duration is not changed but the activities having float are rescheduled so that a uniform demand for the resources is achieved.
Detailed explanation-2: -Critical Path Method. A common leveling technique, this method involves a visual mapping of the project’s ‘critical path’ to decide the start and end dates, dependency and duration, and so on. Critical Chain Management. Fast-Tracking. Project Crashing. 17-Nov-2022