Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are the project manager of a construction company. You know that the builders start painting the walls 30 days after they start installing the drywall. This waiting time can also be referred to as:
A
Lead time
B
Project float
C
Constraint
D
Lag
Explanation: 

Detailed explanation-1: -Businesses can stay on track of their planned schedule and budget with the help of Gantt charts. And if things don’t go as planned, Gantt charts help in identifying the critical tasks that will ensure your project gets completed on time. In project management, Gantt charts are an important tool in planning.

Detailed explanation-2: -What is the best way an IT project manager can deal with a manager who will not listen? Document all communication between the manager and the IT project manager. What is an activity list?