For project scheduling, bar charts show:
A
The level of effort for an activity.
B
Availability of resources assigned to perform project activities.
C
Activity start and end dates, as well as expected durations.
D
Relative priority of activities.
Explanation: 

Detailed explanation-1: -A Gantt chart, commonly used in project management, is one of the most popular and useful ways of showing activities (tasks or events) displayed against time.

Detailed explanation-2: -A Gantt chart is a bar chart that provides a visual view of project tasks scheduled over time. A Gantt chart is used for project planning: it’s a useful way of showing what work is scheduled to be done on specific days.