The organization is about to begin a series of similar projects. The projects will be managed consecutively. Each project involves developing an online cooking video focused on foods appropriate to the month in which they will be released. For example, the summer videos will include picnic food and cool treats, and the December video will feature holiday foods for Hanukkah, Christmas, and Kwanzaa. The project sponsor is adamant that the management plan for each project includes an emphasis on making the best possible use of the lessons learned register. He believes that other projects have not been successful because they failed to take advantage of lessons learned from previously completed projects. The lessons learned register should be updated:
A
At the end of each project phase
B
Throughout the project
C
Weekly
D
At the end of the project
Explanation: 