Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are asked to prepare a budget for completing a project that was started last year and then shelved for six months. All the following would be included in the project budget except:
A
Fixed costs
B
Sunk costs
C
Direct costs
D
Variable costs
Explanation: 

Detailed explanation-1: -Logical relationship Finish-to-finish–the “from” activity must finish before the “to” activity can finish.

Detailed explanation-2: -Which of the following BEST describes what a project charter may be used for when the work is being completed? Explanation: One of the ways to decide if a change should be approved is to determine whether the work falls within the project charter.