Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
You are asked to prepare a budget for completing a project that was started last year and then shelved for six months. All the following would be included in the project budget except:
|
Fixed costs
|
|
Sunk costs
|
|
Direct costs
|
|
Variable costs
|
Explanation:
Detailed explanation-1: -Logical relationship Finish-to-finish–the “from” activity must finish before the “to” activity can finish.
Detailed explanation-2: -Which of the following BEST describes what a project charter may be used for when the work is being completed? Explanation: One of the ways to decide if a change should be approved is to determine whether the work falls within the project charter.