Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
The WBS Dictionary in Scope Management has an equivalent in Schedule Management, which is which of the following
|
The Activity Dictionary
|
|
The Activity Attributes
|
|
The Task Glossary
|
|
The Activity Estimate
|
Explanation:
Detailed explanation-1: -A Work Breakdown Structure (WBS) identifies tasks and deliverables associated with a project. Resources are identified for each item within the WBS that facilitates budgeting as well as assignment of responsibilities. T he WBS can be used to determine the critical path of the project and create the project schedule.
Detailed explanation-2: -Scope baseline is a combination of project scope statement and WBS and WBS dictionary. Scope baseline is a part of the project management plan. Project Scope statement can include: Product Scope.