Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Inputs to the Define Activities process are:
A
Schedule management plan, work breakdown structure, project schedule, and network diagram.
B
Project schedule, resource estimates, progress reports, and change requests.
C
Scope management plan, project network diagram, constraints, and assumptions.
D
Schedule management plan, scope baseline, enterprise environmental factors, and organizational process assets.
Explanation: 

Detailed explanation-1: -What Are the Inputs? Inputs to developing the schedule management plan include the project management plan, the project charter, enterprise environmental factors and organizational process assets.

Detailed explanation-2: -An activity in project management is a stage of the project management plan. It is the lowest level of the project work breakdown structure and is a sub-division of work packages. An Activity contains a list of tasks or actions to be taken in a particular order to convert an input into the appropriate output.

Detailed explanation-3: -This project management process generally includes four phases: initiating, planning, executing, and closing. Some may also include a fifth “monitoring and controlling” phase between the executing and closing stages. By following each step, a project team increases the chance of achieving its goals.