Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
“Which of the following best describes the relationship between standard deviation and risk?
A
There is no relationship.
B
Standard deviation tells you if the estimate is accurate.
C
standard deviation tells you how uncertain the estimate is.
D
Standard deviation tells you if the estimate includes a path.
Explanation: 

Detailed explanation-1: -Answer: C. Standard deviation tells you how uncertain the estimate is.