SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
“Which of the following best describes the relationship between standard deviation and risk?
|
There is no relationship.
|
|
Standard deviation tells you if the estimate is accurate.
|
|
standard deviation tells you how uncertain the estimate is.
|
|
Standard deviation tells you if the estimate includes a path.
|
Explanation:
Detailed explanation-1: -Answer: C. Standard deviation tells you how uncertain the estimate is.
There is 1 question to complete.