Michael is the project manager of the 78GH Project. This project requires several members of the project team to complete a certification class for another project the week of November 2. This class causes some of the project activities on Michael’s activities to be delayed from his target schedule. This is an example of which of the following?
A
Hard logic
B
External dependencies
C
Soft logic
D
Conflict of interest
Explanation: 

Detailed explanation-1: -Which of the following is a correct attribute of the critical path? It determines the earliest completion date.

Detailed explanation-2: -Where is a project manager most likely to experience a subnet? D. Subnets are often included in network templates to summarize common activities in a project.