Scheduling only include estimation of resources
A
False
B
True
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -Project scheduling consists of assigning start and end dates to individual tasks and allocating appropriate resources within an estimated budget. This is what allows you to make sure the team can complete their tasks on time. It only focuses on the tasks, their deadlines and project dependencies.

Detailed explanation-2: -Deliverables. Tasks. Task start and end dates. Task dependencies. Project calendar. Work packages. Task duration and project timeline. Budgets. More items

Detailed explanation-3: -Project Schedule Format #1: Network Diagram. Project Schedule Format #2: Milestone charts. Project Schedule Format #3: Bar charts or Gantt charts. 25-Dec-2022