Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The Control Schedule process for a project:
A
Focuses on starting the project earlier than scheduled to help mitigate schedule risk and to achieve the approved schedule baseline.
B
Is the process of monitoring the status of the project to update the project schedule and managing changes to the schedule baseline.
C
Is concerned mainly with activities that are on the critical path.
D
Should focus primarily on activities that are difficult to carry out
Explanation: 

Detailed explanation-1: -According to PMI, Control Schedule is “the process of monitoring the status of the project to update the project schedule and manage changes to the schedule baseline.”

Detailed explanation-2: -Control Scope The Control Scope process involves monitoring the status of the project and managing changes to the scope. The table below shows the Inputs, Tools and Techniques, and Outputs of the Scope Control process.

Detailed explanation-3: -Control Costs are the process of monitoring the status of the project to update the project costs and manage changes to the cost baseline. The key benefit of this process is that it provides the means to recognize variance from the plan in order to take corrective action and minimize risk.