Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You have taken over a project during project planning and have discovered that six individuals have signed the project charter. Which of the following should most concern you?
A
Who will be a member of the change control board
B
Spending more time on configuration management
C
Getting a single project sponsor
D
Determining the reporting structure
Explanation: 

Detailed explanation-1: -You are taking over a project during project planning and discover that six individuals have signed the project charter. Which of the following should MOST concern you? Explanation: Determining who will be on the change control board and determining the reporting structure may have already been done.

Detailed explanation-2: -A project charter names the project manager and defines the authority of the project manager. It gives the project manager the power to utilize organizational resources to accomplish the project objectives.

Detailed explanation-3: -Project Management/PMBOK/Integration Management. Integration management is a collection of processes required to ensure that the various elements of the projects are properly coordinated. It involves making trade-offs among competing objectives and alternatives to meet or exceed stakeholder needs and expectations.

Detailed explanation-4: -Project Scope Management: Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

There is 1 question to complete.