Question 18 of 100Question ID:612613You are using work performance data generated during execution to determine if new individual project risks have occurred and if your risk management approach is still appropriate. You have also reviewed the contingency reserves to see if they require any modification. As part of your documentation of this process, you have added an issue you discovered to the issue log to ensure it is investigated and resolved.What else might require an update as part of this process?
A
AProject schedule
B
BCost forecasts
C
CEnterprise environmental factors
D
DOrganizational process assets
Explanation: 

Detailed explanation-1: -PMBOK® Guide Sixth Edition defines work Performance Data as: The raw observations and measurements – identied during activities being performed to carry out the project work.

Detailed explanation-2: -Work Performance Data is raw observations and measurements about the project’s current status. On the other hand, Work Performance Information compares the actual and planned values. Both terms are closely related to each other and they help to understand the project’s current status.