SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
ATechnical performance analysis
|
|
BReserve analysis
|
|
CContingency analysis
|
|
DRisk audit
|
Detailed explanation-1: -A risk register, sometimes known as a risk log, is an important component of the overall risk management framework. Created during the early stages of a project, the risk register is a tool that helps you track issues and address them as they arise.
Detailed explanation-2: -A risk register document, otherwise known as a risk register log, tracks potential risks specifically within a project.
Detailed explanation-3: -Ideally, you should create your risk management plan during the project planning phase. That way, you can best identify any risks and their potential impact and monitor those risks during the project. Instead of being caught unaware, you’ll have your eye on those risks in case they do become troublesome.