Question 36 of 100Question ID:612333During project execution of a high priority project, a previously identified risk is realized. The project manager sends an email to the risk owner and receives an automated response indicating that this individual will be out of the country on vacation for the next two weeks. The risk owner did not disclose a backup contact to use during the interim.What should the project manager do first?
A
ACapture the problem in the issue resolution register
B
BUpdate the communications management plan
C
CSubmit a change request
D
DRecord the information in the issue log
Explanation: 

Detailed explanation-1: -A risk register is a tool in risk management and project management. It is used to identify potential risks in a project or an organization, sometimes to fulfill regulatory compliance but mostly to stay on top of potential issues that can derail intended outcomes.

Detailed explanation-2: -What risks for a project have the highest priority? Risks that have the highest priority are those on the critical path and those that have high degree of impact and high likelihood of occurance.